$1,521.39 / EA
Level 2 EV charger installation costs about $1,521.39 each installed. This is a published starting point and varies by region and job.
National average
Enter a 5-digit ZIP for local pricing.
Adjust labor, markup, and materials for your own bids in a private library. Free, no card required. Published rates stay public while your hours and quotes stay private. See Unit rate estimating software.
RES-SEO-13-07 · MasterFormat 26 31 13 · EA
What’s in this rate
This unit is installing one Level 2, 240-volt hardwired residential EV charger on a new 60-amp dedicated circuit at an existing garage, from an existing panel that already has the spare capacity. The electrician mounts the charger, runs 50 feet of 6-gauge copper in 3/4-inch conduit with couplings, connectors, and straps, lands a 60-amp two-pole breaker, and commissions the 48-amp charge setting. It is priced each. A panel upgrade, a longer or underground run, and permits are separate units.
Includes
- Level 2 hardwired residential EV charger
- 50 feet of 6-gauge copper in 3/4-inch conduit, with couplings, connectors, and straps
- 60-amp two-pole breaker
- Mount, pull, land, and commission at the 48-amp setting
Excludes
- Panel upgrade
- A new panel or service
- Permits
- A pedestal or a run longer than 50 feet
- Underground runs
- The vehicle
Build-up
- Electrician, 6 hr × $58.00
- $348.00
- Material and small tools
- $909.35
- Direct rate (labor, material, and tools)
- $1,257.35 / EA
- Overhead 10% of direct
- $125.74
- Fee 10% of (direct and overhead)
- $138.30
- Loaded rate
- $1,521.39 / EA
Worked extension: 1 EA × $1,521.39 = $1,521.39 loaded for 1 EA. Quantity is a worked extension.