Overflow primary scupper

$275.58 / EA

RF-224 · MasterFormat 07 72 00 · EA

What’s in this rate

This unit covers Overflow primary scupper, measured per each. The roofer sets the overflow primary scupper at the designated wall or parapet opening, seals flanges to the roofing and wall faces, and checks free overflow discharge. The rate covers the listed material, 5.00% material waste, labor, and small tools. through-parapet box scupper, collector-box scupper, overflow box scupper, through-wall scupper, primary drain, conductor head are separate units.

Includes

  • overflow primary scupper assembly with flanges, fasteners, and sealant
  • layout, ordinary surface preparation, and installation described above
  • stated material waste and small tools

Excludes

  • through-parapet box scupper
  • collector-box scupper
  • overflow box scupper
  • through-wall scupper
  • primary drain
  • conductor head
  • tax / freight
  • after-hours, premium access, and hazardous-material handling

Build-up

Labor 1.15 hr × $65.00 wage and burden
$74.75
Material and small tools
$153.00
Direct rate (labor, material, and tools)
$227.75 / EA
Overhead 10% of direct
$22.78
Fee 10% of (direct and overhead)
$25.05
Loaded rate
$275.58 / EA