RTU set curb-ready

$5,636.30 / EA

HV-045 · MasterFormat 23 74 00 · EA

What’s in this rate

This unit is setting one packaged rooftop unit onto a prepared curb. The HVAC technician places and levels the unit on the curb, connects duct collars, and leaves it ready for power, gas, and controls. The rate is per each RTU set. Curb fabrication and set, crane lift premiums, electrical power, gas piping, and roofing flash beyond the curb seal share are separate units.

Includes

  • packaged rooftop unit (class mid)
  • set and level on prepared curb
  • duct collar connect allowance
  • curb gasket / seal share
  • small tools

Excludes

  • rooftop curb set (see rooftop-curb-set)
  • crane / helicopter lift premium
  • electrical power
  • gas piping
  • controls / BAS beyond unit lead
  • roofing flash beyond curb seal share

Build-up

Labor 6 hr × $68.00 wage and burden
$408.00
Material and small tools
$4,250.10
Direct rate (labor, material, and tools)
$4,658.10 / EA
Overhead 10% of direct
$465.81
Fee 10% of (direct and overhead)
$512.39
Loaded rate
$5,636.30 / EA

Use this in a private library

Create a free account to keep your own hours, burden, and supplier quotes behind a login. Published rates stay public. Your own hours and quotes stay private.