Half-high CMU partition

$12.95 / SF

MS-D3-003 · MasterFormat 04 22 00 · SF

What’s in this rate

This unit covers Half-high CMU partition, measured per square foot. The bricklayer lays half-high CMU as an interior partition with tooled joints. The rate covers the listed material, 5.00% material waste, labor, and small tools. half-high CMU wall (field), nonloadbearing CMU partition, CMU knee wall, drywall partition are separate units.

Includes

  • CMU units / block as specified
  • Type S mortar allocation
  • bed and head joints with tooling
  • layout and installation described above
  • stated material waste and small tools

Excludes

  • cmu-half-high-wall (field)
  • drywall partition
  • paint-cmu-*
  • tax / freight
  • after-hours, premium access, and hazardous-material handling

Build-up

Labor 0.12 hr × $52.00 wage and burden
$6.24
Material and small tools
$4.46
Direct rate (labor, material, and tools)
$10.70 / SF
Overhead 10% of direct
$1.07
Fee 10% of (direct and overhead)
$1.18
Loaded rate
$12.95 / SF