Broom-finish sidewalk

$5.48 / SF

CN-193 · MasterFormat 03 35 00 · SF

What’s in this rate

This unit is broom-finishing one square foot of prepared sidewalk slab. The concrete finisher edges, joints, and brooms the surface. Ramp broom finish, curb pour, and slab placement are separate units.

Includes

  • broom-finish cure allowance
  • edge and joint tool allowance
  • edge, joint, and broom sidewalk surface
  • small tools

Excludes

  • slab pour
  • broom-finish ramp
  • curb pour
  • reinforcing steel
  • base preparation

Build-up

Labor 0.08 hr × $46.00 wage and burden
$3.68
Material and small tools
$0.85
Direct rate (labor, material, and tools)
$4.53 / SF
Overhead 10% of direct
$0.45
Fee 10% of (direct and overhead)
$0.50
Loaded rate
$5.48 / SF