Ductbank encasement

$18.49 / CF

CN-100 · MasterFormat 03 30 00 · CF

What’s in this rate

This unit is placing one cubic foot of concrete encasement around prepared utility ductbank. The cement mason places and consolidates the encasement to provide a continuous protective mass. Ducts, trenching, bedding, testing, and backfill are separate units.

Includes

  • ready-mix encasement concrete with 5% waste
  • place and consolidate around installed ductbank
  • small tools

Excludes

  • ducts
  • conduit
  • trenching
  • bedding
  • testing
  • backfill
  • rebar
  • excavation

Build-up

Labor 0.18 hr × $48.00 wage and burden
$8.64
Material and small tools
$6.64
Direct rate (labor, material, and tools)
$15.28 / CF
Overhead 10% of direct
$1.53
Fee 10% of (direct and overhead)
$1.68
Loaded rate
$18.49 / CF