Place & finish equipment pad

$9.47 / SF

CN-018 · MasterFormat 03 30 00 · SF

What’s in this rate

This unit is placing and finishing a 6-inch equipment pad. The mason places ready-mix, then edges, floats, and finishes the pad. The rate is per square foot. Edge forms, rebar or mesh, anchor bolts, and equipment setting are separate units.

Includes

  • Ready-mix for 6-inch pad with waste
  • Place, edge, float, and finish
  • Small tools

Excludes

  • Edge forms
  • Rebar or mesh
  • Anchor bolts
  • Equipment setting

Build-up

Labor 0.1 hr × $48.00 wage and burden
$4.80
Material and small tools
$3.03
Direct rate (labor, material, and tools)
$7.83 / SF
Overhead 10% of direct
$0.78
Fee 10% of (direct and overhead)
$0.86
Loaded rate
$9.47 / SF

Use this in a private library

Create a free account to keep your own hours, burden, and supplier quotes behind a login. Published rates stay public. Your own hours and quotes stay private.