Place & finish equipment pad
$9.47 / SF
CN-018 · MasterFormat 03 30 00 · SF
What’s in this rate
This unit is placing and finishing a 6-inch equipment pad. The mason places ready-mix, then edges, floats, and finishes the pad. The rate is per square foot. Edge forms, rebar or mesh, anchor bolts, and equipment setting are separate units.
Includes
- Ready-mix for 6-inch pad with waste
- Place, edge, float, and finish
- Small tools
Excludes
- Edge forms
- Rebar or mesh
- Anchor bolts
- Equipment setting
Build-up
- Labor 0.1 hr × $48.00 wage and burden
- $4.80
- Material and small tools
- $3.03
- Direct rate (labor, material, and tools)
- $7.83 / SF
- Overhead 10% of direct
- $0.78
- Fee 10% of (direct and overhead)
- $0.86
- Loaded rate
- $9.47 / SF