Pier footing pour
$27.16 / CF
CN-157 · MasterFormat 03 30 00 · CF
What’s in this rate
This unit is placing one cubic foot of concrete for a pier footing at a prepared excavation. The cement mason places, consolidates, and finishes the footing mass. Excavation, reinforcing steel, pier shafts, pier caps, and anchors are separate units.
Includes
- ready-mix concrete
- form and curing-material allowance
- place, consolidate, and finish pier footing
- small tools
Excludes
- excavation
- reinforcing steel
- pier shaft
- pier cap
- anchors and embeds
- testing
Build-up
- Labor 0.29 hr × $48.00 wage and burden
- $13.92
- Material and small tools
- $8.53
- Direct rate (labor, material, and tools)
- $22.45 / CF
- Overhead 10% of direct
- $2.24
- Fee 10% of (direct and overhead)
- $2.47
- Loaded rate
- $27.16 / CF