Raft foundation pour

$25.98 / CF

CN-185 · MasterFormat 03 30 00 · CF

What’s in this rate

This unit is placing one cubic foot of concrete into a prepared raft-foundation pour. The cement mason places, consolidates, and finishes the raft mass. Excavation, formwork, reinforcing steel, waterproofing, and testing are separate units.

Includes

  • ready-mix concrete
  • curing-material allowance
  • place, consolidate, and finish raft foundation
  • small tools

Excludes

  • excavation
  • formwork
  • reinforcing steel
  • waterproofing
  • pump mobilization
  • testing

Build-up

Labor 0.27 hr × $48.00 wage and burden
$12.96
Material and small tools
$8.51
Direct rate (labor, material, and tools)
$21.47 / CF
Overhead 10% of direct
$2.15
Fee 10% of (direct and overhead)
$2.36
Loaded rate
$25.98 / CF