CMU elevator shaft wall

$18.80 / SF

MS-D2-006 · MasterFormat 04 22 00 · SF

What’s in this rate

This unit covers CMU elevator shaft wall, measured per square foot. The bricklayer lays CMU elevator shaft walls plumb with tooled joints. The rate covers the listed material, 5.00% material waste, labor, and small tools. field CMU wall, stair shaft CMU, paint-cmu finishes, elevator equipment are separate units.

Includes

  • cmu elevator shaft wall units / block
  • Type S mortar allocation
  • bed and head joints with tooling
  • layout and installation described above
  • stated material waste and small tools

Excludes

  • field CMU wall
  • elevator equipment
  • paint-cmu-*
  • grout / rebar
  • tax / freight
  • after-hours, premium access, and hazardous-material handling

Build-up

Labor 0.16 hr × $52.00 wage and burden
$8.32
Material and small tools
$7.22
Direct rate (labor, material, and tools)
$15.54 / SF
Overhead 10% of direct
$1.55
Fee 10% of (direct and overhead)
$1.71
Loaded rate
$18.80 / SF