CMU elevator shaft wall
$18.80 / SF
MS-D2-006 · MasterFormat 04 22 00 · SF
What’s in this rate
This unit covers CMU elevator shaft wall, measured per square foot. The bricklayer lays CMU elevator shaft walls plumb with tooled joints. The rate covers the listed material, 5.00% material waste, labor, and small tools. field CMU wall, stair shaft CMU, paint-cmu finishes, elevator equipment are separate units.
Includes
- cmu elevator shaft wall units / block
- Type S mortar allocation
- bed and head joints with tooling
- layout and installation described above
- stated material waste and small tools
Excludes
- field CMU wall
- elevator equipment
- paint-cmu-*
- grout / rebar
- tax / freight
- after-hours, premium access, and hazardous-material handling
Build-up
- Labor 0.16 hr × $52.00 wage and burden
- $8.32
- Material and small tools
- $7.22
- Direct rate (labor, material, and tools)
- $15.54 / SF
- Overhead 10% of direct
- $1.55
- Fee 10% of (direct and overhead)
- $1.71
- Loaded rate
- $18.80 / SF
Related rates
Use this in a private library
Create a free account to keep your own hours, burden, and supplier quotes behind a login. Published rates stay public. Your own hours and quotes stay private.
