CMU pier

$220.10 / EA

MS-008 · MasterFormat 04 22 00 · EA

What’s in this rate

This unit covers CMU pier, measured per each. The bricklayer stacks and plumbs a CMU pier or column to the scoped height with tooled joints. The rate covers the listed material, 5.00% material waste, labor, and small tools. grout-filled CMU cell, vertical rebar in CMU, CMU bond beam block, brick pier are separate units.

Includes

  • CMU units for pier/column stack
  • Type S mortar
  • plumb and joint tooling
  • layout and installation described above
  • stated material waste and small tools

Excludes

  • grout fill and rebar
  • bond beam course
  • brick pier
  • cap / coping
  • tax / freight
  • after-hours, premium access, and hazardous-material handling

Build-up

Labor 2.5 hr × $52.00 wage and burden
$130.00
Material and small tools
$51.90
Direct rate (labor, material, and tools)
$181.90 / EA
Overhead 10% of direct
$18.19
Fee 10% of (direct and overhead)
$20.01
Loaded rate
$220.10 / EA

Use this in a private library

Create a free account to keep your own hours, burden, and supplier quotes behind a login. Published rates stay public. Your own hours and quotes stay private.