Grout-filled CMU cell
$14.17 / EA
MS-010 · MasterFormat 04 22 00 · EA
What’s in this rate
This unit covers Grout-filled CMU cell, measured per each. The bricklayer places masonry grout into one cleaned CMU cell and consolidates as scoped. The rate covers the listed material, 3.00% material waste, labor, and small tools. masonry grout place (CF), CMU wall lay, vertical rebar in CMU, concrete-nonshrink-grout are separate units.
Includes
- masonry grout for one cell
- placement into cleaned cell
- layout and installation described above
- stated material waste and small tools
Excludes
- CMU wall lay
- vertical rebar (separate)
- full-height masonry-grout-place by CF
- concrete nonshrink grout
- tax / freight
- after-hours, premium access, and hazardous-material handling
Build-up
- Labor 0.15 hr × $52.00 wage and burden
- $7.80
- Material and small tools
- $3.91
- Direct rate (labor, material, and tools)
- $11.71 / EA
- Overhead 10% of direct
- $1.17
- Fee 10% of (direct and overhead)
- $1.29
- Loaded rate
- $14.17 / EA