Broom-finish ramp
$5.91 / SF
CN-178 · MasterFormat 03 35 00 · SF
What’s in this rate
This unit is applying one square foot of broom finish on a prepared concrete ramp. The concrete finisher edges, brooms, and cures the traction face. Placement, radius curb, mountable curb, and coatings are separate units.
Includes
- broom-finish and curing-compound allowance
- edge-tool and masking allowance
- edge, broom, and cure ramp face
- small tools
Excludes
- concrete placement
- radius curb form
- mountable curb
- coatings
- handrails
Build-up
- Labor 0.085 hr × $46.00 wage and burden
- $3.91
- Material and small tools
- $0.97
- Direct rate (labor, material, and tools)
- $4.88 / SF
- Overhead 10% of direct
- $0.49
- Fee 10% of (direct and overhead)
- $0.54
- Loaded rate
- $5.91 / SF