Broom-finish ramp

$5.91 / SF

CN-178 · MasterFormat 03 35 00 · SF

What’s in this rate

This unit is applying one square foot of broom finish on a prepared concrete ramp. The concrete finisher edges, brooms, and cures the traction face. Placement, radius curb, mountable curb, and coatings are separate units.

Includes

  • broom-finish and curing-compound allowance
  • edge-tool and masking allowance
  • edge, broom, and cure ramp face
  • small tools

Excludes

  • concrete placement
  • radius curb form
  • mountable curb
  • coatings
  • handrails

Build-up

Labor 0.085 hr × $46.00 wage and burden
$3.91
Material and small tools
$0.97
Direct rate (labor, material, and tools)
$4.88 / SF
Overhead 10% of direct
$0.49
Fee 10% of (direct and overhead)
$0.54
Loaded rate
$5.91 / SF