Construction joint key

$8.66 / LF

CN-176 · MasterFormat 03 11 00 · LF

What’s in this rate

This unit is setting one linear foot of construction-joint key at a prepared slab or wall pour break. The cement mason cuts, sets, and secures the keyed joint former. Concrete placement, isolation joints, waterstop, and sealant are separate units.

Includes

  • keyed joint former and lumber allowance
  • fastener and release-agent allowance
  • cut, set, and secure joint key
  • small tools

Excludes

  • concrete placement
  • isolation joint
  • waterstop
  • joint sealant
  • carton forms

Build-up

Labor 0.09 hr × $48.00 wage and burden
$4.32
Material and small tools
$2.83
Direct rate (labor, material, and tools)
$7.15 / LF
Overhead 10% of direct
$0.72
Fee 10% of (direct and overhead)
$0.79
Loaded rate
$8.66 / LF