Drilled pier pour
$27.62 / CF
CN-167 · MasterFormat 03 30 00 · CF
What’s in this rate
This unit is placing one cubic foot of concrete into a prepared drilled-pier shaft. The cement mason places, consolidates, and finishes the pier. Drilling, casing, reinforcing steel, pier caps, and anchors are separate units.
Includes
- ready-mix concrete
- tremie and curing-material allowance
- place, consolidate, and finish drilled pier
- small tools
Excludes
- drilling and excavation
- casing
- reinforcing steel
- pier cap
- anchors and embeds
- testing
Build-up
- Labor 0.3 hr × $48.00 wage and burden
- $14.40
- Material and small tools
- $8.43
- Direct rate (labor, material, and tools)
- $22.83 / CF
- Overhead 10% of direct
- $2.28
- Fee 10% of (direct and overhead)
- $2.51
- Loaded rate
- $27.62 / CF