Drilled pier pour

$27.62 / CF

CN-167 · MasterFormat 03 30 00 · CF

What’s in this rate

This unit is placing one cubic foot of concrete into a prepared drilled-pier shaft. The cement mason places, consolidates, and finishes the pier. Drilling, casing, reinforcing steel, pier caps, and anchors are separate units.

Includes

  • ready-mix concrete
  • tremie and curing-material allowance
  • place, consolidate, and finish drilled pier
  • small tools

Excludes

  • drilling and excavation
  • casing
  • reinforcing steel
  • pier cap
  • anchors and embeds
  • testing

Build-up

Labor 0.3 hr × $48.00 wage and burden
$14.40
Material and small tools
$8.43
Direct rate (labor, material, and tools)
$22.83 / CF
Overhead 10% of direct
$2.28
Fee 10% of (direct and overhead)
$2.51
Loaded rate
$27.62 / CF