Elevator pit drain

$18.69 / EA

CN-211 · MasterFormat 03 30 00 · EA

What’s in this rate

This unit is setting one elevator pit drain into a prepared pit floor. The cement mason sets, levels, and secures the drain body and strainer. Pit sump, pit wall form, drain piping, sump pump, waterproofing, and testing are separate units.

Includes

  • elevator pit drain body and strainer
  • grout and seal allowance
  • set, level, and secure pit drain
  • small tools

Excludes

  • pit sump
  • pit wall form
  • drain piping
  • sump pump
  • waterproofing
  • testing

Build-up

Labor 0.175 hr × $48.00 wage and burden
$8.40
Material and small tools
$7.05
Direct rate (labor, material, and tools)
$15.45 / EA
Overhead 10% of direct
$1.54
Fee 10% of (direct and overhead)
$1.70
Loaded rate
$18.69 / EA