Caisson bell pour

$28.64 / CF

CN-212 · MasterFormat 03 30 00 · CF

What’s in this rate

This unit is placing one cubic foot of concrete into a prepared caisson bell. The cement mason places, consolidates, and finishes the belled mass. Drilling, casing, reinforcing steel, shaft pour, pier caps, and testing are separate units.

Includes

  • ready-mix concrete
  • tremie and curing-material allowance
  • place, consolidate, and finish caisson bell
  • small tools

Excludes

  • drilling and excavation
  • casing
  • reinforcing steel
  • caisson shaft pour
  • pier cap
  • testing

Build-up

Labor 0.31 hr × $48.00 wage and burden
$14.88
Material and small tools
$8.79
Direct rate (labor, material, and tools)
$23.67 / CF
Overhead 10% of direct
$2.37
Fee 10% of (direct and overhead)
$2.60
Loaded rate
$28.64 / CF