Elevator pit sump

$22.49 / EA

CN-196 · MasterFormat 03 30 00 · EA

What’s in this rate

This unit is setting one elevator pit sump in a prepared pit floor. The cement mason positions, levels, and secures the sump ready for the pit pour. Pit wall formwork, pit floor pour, waterproofing, and sump pump equipment are separate units.

Includes

  • elevator pit sump liner or form kit
  • grout and fastener allowance
  • position, level, and secure sump
  • small tools

Excludes

  • pit wall formwork
  • pit floor pour
  • waterproofing
  • sump pump equipment
  • drain piping
  • excavation

Build-up

Labor 0.21 hr × $48.00 wage and burden
$10.08
Material and small tools
$8.51
Direct rate (labor, material, and tools)
$18.59 / EA
Overhead 10% of direct
$1.86
Fee 10% of (direct and overhead)
$2.04
Loaded rate
$22.49 / EA