Elevator pit sump basin
$20.80 / EA
CN-226 · MasterFormat 03 30 00 · EA
What’s in this rate
This unit is setting one elevator-pit sump basin into a prepared pit floor. The cement mason positions, levels, and secures the basin ready for connection. Pit drains, pit wall forms, sump pumps, waterproofing, and piping are separate units.
Includes
- elevator pit sump basin body
- grout and seal allowance
- set, level, and secure sump basin
- small tools
Excludes
- elevator pit drain
- pit wall form
- sump pump
- drain piping
- waterproofing
- testing
Build-up
- Labor 0.185 hr × $48.00 wage and burden
- $8.88
- Material and small tools
- $8.31
- Direct rate (labor, material, and tools)
- $17.19 / EA
- Overhead 10% of direct
- $1.72
- Fee 10% of (direct and overhead)
- $1.89
- Loaded rate
- $20.80 / EA