Elevator pit sump basin

$20.80 / EA

CN-226 · MasterFormat 03 30 00 · EA

What’s in this rate

This unit is setting one elevator-pit sump basin into a prepared pit floor. The cement mason positions, levels, and secures the basin ready for connection. Pit drains, pit wall forms, sump pumps, waterproofing, and piping are separate units.

Includes

  • elevator pit sump basin body
  • grout and seal allowance
  • set, level, and secure sump basin
  • small tools

Excludes

  • elevator pit drain
  • pit wall form
  • sump pump
  • drain piping
  • waterproofing
  • testing

Build-up

Labor 0.185 hr × $48.00 wage and burden
$8.88
Material and small tools
$8.31
Direct rate (labor, material, and tools)
$17.19 / EA
Overhead 10% of direct
$1.72
Fee 10% of (direct and overhead)
$1.89
Loaded rate
$20.80 / EA