Equipment pad elevated

$180.20 / EA

CN-050 · MasterFormat 03 30 00 · EA

What’s in this rate

This unit is placing and finishing one elevated equipment pad with a formed curb or lip for mechanical equipment. The cement mason forms the pad envelope share, places, edges, and finishes ready for cure. The rate is per each typical elevated pad. Flat equipment pad by the square foot, housekeeping pad densify, and equipment setting are separate units.

Includes

  • ready-mix concrete for typical elevated pad (~0.30 CY) with 5% waste
  • form lumber share for curb/lip
  • place, edge, float, and finish
  • small tools

Excludes

  • flat equipment pad SF (buy concrete-pad-equipment)
  • housekeeping pad EA (buy concrete-housekeeping-pad)
  • excavation / base
  • rebar / anchors / equipment setting

Build-up

Labor 1.5 hr × $48.00 wage and burden
$72.00
Material and small tools
$76.93
Direct rate (labor, material, and tools)
$148.93 / EA
Overhead 10% of direct
$14.89
Fee 10% of (direct and overhead)
$16.38
Loaded rate
$180.20 / EA