Boiler housekeeping pad

$17.52 / SF

CN-219 · MasterFormat 03 30 00 · SF

What’s in this rate

This unit is forming, placing, and finishing one square foot of concrete housekeeping pad for boiler equipment on prepared base. The cement mason forms the raised edge, places, and finishes the pad. Base, reinforcement, equipment anchors, vibration isolation, and equipment setting are separate units.

Includes

  • ready-mix concrete
  • edge-form and curing-material allowance
  • form, place, and finish boiler pad
  • small tools

Excludes

  • subgrade and base
  • reinforcing steel
  • equipment anchors
  • vibration isolation
  • equipment setting
  • chiller housekeeping pad

Build-up

Labor 0.17 hr × $48.00 wage and burden
$8.16
Material and small tools
$6.32
Direct rate (labor, material, and tools)
$14.48 / SF
Overhead 10% of direct
$1.45
Fee 10% of (direct and overhead)
$1.59
Loaded rate
$17.52 / SF