Hydrodemolition prep

$5.60 / SF

Hydrodemolition prep costs about $5.60 per square foot installed. This is a published starting point and varies by region and job.

CN-104 · MasterFormat 03 01 00 · SF

Dumpster and trailer prices

These haul prices are separate from the unit rate. Omaha, Nebraska is the 1.00 baseline. Another state uses that state's cost factor. Loaded is the direct price times 1.21, rounded half-up once.

Omaha, Nebraska

  • 10-yard dumpster direct $232.50, loaded $281.33.
  • 20-yard dumpster direct $325.00, loaded $393.25.
  • 30-yard dumpster direct $405.00, loaded $490.05.
  • Trailer trip direct $204.30, loaded $247.20. Tip $51.65 per ton direct, $62.50 per ton loaded.
  • Overage direct $70.00 per ton, loaded $84.70 per ton.

Texas

  • 10-yard dumpster direct $220.88, loaded $267.26.
  • 20-yard dumpster direct $308.75, loaded $373.59.
  • 30-yard dumpster direct $384.75, loaded $465.55.
  • Trailer trip direct $194.09, loaded $234.84. Tip $49.07 per ton direct, $59.37 per ton loaded.
  • Overage direct $66.50 per ton, loaded $80.47 per ton.

California

  • 10-yard dumpster direct $279.00, loaded $337.59.
  • 20-yard dumpster direct $390.00, loaded $471.90.
  • 30-yard dumpster direct $486.00, loaded $588.06.
  • Trailer trip direct $245.16, loaded $296.64. Tip $61.98 per ton direct, $75.00 per ton loaded.
  • Overage direct $84.00 per ton, loaded $101.64 per ton.

Open the dumpster price calculator for another state.

What’s in this rate

This unit is preparing one square foot of concrete face by controlled hydrodemolition for a follow-on repair. The cement mason removes unsound material and leaves a clean, sound substrate. Water management, repair concrete, disposal, and engineering are separate units.

Includes

  • hydrodemolition consumable/equipment share
  • remove unsound face and expose substrate
  • small tools

Excludes

  • repair concrete
  • rebar replacement
  • water collection/disposal
  • containment
  • engineering

Build-up

Labor 0.07 hr × $48.00 wage and burden
$3.36
Material and small tools
$1.27
Direct rate (labor, material, and tools)
$4.63 / SF
Overhead 10% of direct
$0.46
Fee 10% of (direct and overhead)
$0.51
Loaded rate
$5.60 / SF