Pier / spread footing place
$102.76 / EA
CN-026 · MasterFormat 03 30 00 · EA
What’s in this rate
This unit is placing one isolated pier or spread footing. The mason places and consolidates ready-mix in the footing. The rate is per footing. Excavation, forms, footing rebar, and a continuous footing billed by the foot are separate units.
Includes
- Ready-mix for one isolated pier or spread footing
- Place and consolidate
- Small tools
Excludes
- Excavation
- Forms
- Footing rebar
- Continuous footing billed by the foot
Build-up
- Labor 0.75 hr × $48.00 wage and burden
- $36.00
- Material and small tools
- $48.93
- Direct rate (labor, material, and tools)
- $84.93 / EA
- Overhead 10% of direct
- $8.49
- Fee 10% of (direct and overhead)
- $9.34
- Loaded rate
- $102.76 / EA