Pier / spread footing place

$102.76 / EA

CN-026 · MasterFormat 03 30 00 · EA

What’s in this rate

This unit is placing one isolated pier or spread footing. The mason places and consolidates ready-mix in the footing. The rate is per footing. Excavation, forms, footing rebar, and a continuous footing billed by the foot are separate units.

Includes

  • Ready-mix for one isolated pier or spread footing
  • Place and consolidate
  • Small tools

Excludes

  • Excavation
  • Forms
  • Footing rebar
  • Continuous footing billed by the foot

Build-up

Labor 0.75 hr × $48.00 wage and burden
$36.00
Material and small tools
$48.93
Direct rate (labor, material, and tools)
$84.93 / EA
Overhead 10% of direct
$8.49
Fee 10% of (direct and overhead)
$9.34
Loaded rate
$102.76 / EA