Sonotube pier pour

$27.18 / CF

CN-152 · MasterFormat 03 30 00 · CF

What’s in this rate

This unit is placing one cubic foot of concrete in a prepared fiber tube pier form. The cement mason places, consolidates, and finishes the pier top. Excavation, tube setup beyond the allowance, reinforcement, anchors, and testing are separate units.

Includes

  • ready-mix concrete
  • fiber tube-form allowance
  • place, consolidate, and finish pier
  • small tools

Excludes

  • excavation and drilling
  • reinforcing steel
  • anchors and embeds
  • tube installation beyond allowance
  • pump mobilization
  • testing

Build-up

Labor 0.28 hr × $48.00 wage and burden
$13.44
Material and small tools
$9.02
Direct rate (labor, material, and tools)
$22.46 / CF
Overhead 10% of direct
$2.25
Fee 10% of (direct and overhead)
$2.47
Loaded rate
$27.18 / CF