Transformer pad

$210.78 / EA

CN-061 · MasterFormat 03 30 00 · EA

What’s in this rate

This unit is placing and finishing one electrical transformer pad. The cement mason forms the pad envelope share, places, edges, and finishes ready for cure. The rate is per each typical transformer pad. Housekeeping pad, elevated equipment pad, and equipment setting are separate units.

Includes

  • ready-mix concrete for typical transformer pad (~0.40 CY) with 5% waste
  • form lumber share
  • place, edge, float, and finish
  • small tools

Excludes

  • housekeeping pad (buy concrete-housekeeping-pad)
  • elevated equipment pad (buy concrete-equipment-pad-elevated)
  • excavation / base
  • rebar / anchors / equipment setting

Build-up

Labor 1.75 hr × $48.00 wage and burden
$84.00
Material and small tools
$90.20
Direct rate (labor, material, and tools)
$174.20 / EA
Overhead 10% of direct
$17.42
Fee 10% of (direct and overhead)
$19.16
Loaded rate
$210.78 / EA