Foundation wall backfill, free-draining

$52.11 / CY

Foundation wall backfill, free-draining costs about $52.11 per cubic yard installed. This is a published starting point and varies by region and job.

EW-049 · MasterFormat 31 23 23 · CY

What’s in this rate

This unit covers Foundation wall backfill, free-draining, measured per cubic yard. The crew places delivered free-draining granular backfill against foundation walls in lifts and plate-compacts it. The rate covers the listed material, labor, and small tools. Native backfill, waterproofing, drainage board, and footing drains stay on their own units.

Includes

  • free-draining granular backfill delivered (1.25 LCY/CCY)
  • place in lifts
  • plate compaction
  • operator and laborer time and equipment listed in the build-up
  • stated material waste and small tools

Excludes

  • waterproofing / dampproofing / drainage mat
  • footing drain pipe
  • filter fabric wrap
  • tax / freight beyond the stated delivered material prices
  • after-hours, premium access, and contaminated / hazardous soil handling
  • geotechnical testing, surveying / staking, and permits

Build-up

Operator, 0.035 hr × $53.00
$1.86
Laborer, 0.08 hr × $41.00
$3.28
Material and small tools
$35.05
Equipment, skid steer / compact track loader, 0.035 hr per unit
$1.92
Equipment, vibratory plate compactor, 0.08 hr per unit
$0.96
Direct rate (labor, material, equipment, and tools)
$43.07 / CY
Overhead 10% of direct
$4.31
Fee 10% of (direct and overhead)
$4.73
Loaded rate
$52.11 / CY

Worked extension: 100 CY of commercial foundation wall backfill, free-draining × $52.11 = $5,211.00 loaded for 100 CY. Quantity is a worked extension.