Earthwork unit rates
Published earthwork unit rates, Division 31: clearing, erosion control, excavation, haul, fill, grading, and trench backfill. Each page is one unit with a loaded price.
Also see electrical unit rates, low-voltage unit rates, roofing unit rates, drywall unit rates, painting unit rates, concrete unit rates, flooring unit rates, plumbing unit rates, HVAC unit rates, fire protection unit rates, masonry unit rates, and structural steel unit rates.
- Aggregate base course, 10 in compacted$1.81 / SFIncludes 10% overhead and 10% fee
- Aggregate base course, 12 in compacted$2.17 / SFIncludes 10% overhead and 10% fee
- Aggregate base, 4 in$0.74 / SFIncludes 10% overhead and 10% fee
- Aggregate base, 6 in$1.10 / SFIncludes 10% overhead and 10% fee
- Aggregate base, 8 in$1.44 / SFIncludes 10% overhead and 10% fee
- Biaxial geogrid, Type 1 (BX1100 class)$0.44 / SFIncludes 10% overhead and 10% fee
- Biaxial geogrid, Type 2 (BX1200 class)$0.62 / SFIncludes 10% overhead and 10% fee
- Bulk excavation, common earth$2.51 / CYIncludes 10% overhead and 10% fee
- Bulk excavation, sand and loose granular soil$2.08 / CYIncludes 10% overhead and 10% fee
- Bulk excavation, stiff clay$3.34 / CYIncludes 10% overhead and 10% fee
- Clearing and grubbing, light brush$0.10 / SFIncludes 10% overhead and 10% fee
- Clearing and grubbing, medium brush and trees$0.15 / SFIncludes 10% overhead and 10% fee
- Clearing and grubbing, wooded$0.24 / SFIncludes 10% overhead and 10% fee
- Common fill, place and compact, 12 in lifts$2.13 / CYIncludes 10% overhead and 10% fee
- Common fill, place and compact, 18 in lifts$1.75 / CYIncludes 10% overhead and 10% fee
- Concrete washout container, prefabricated 4 ft x 4 ft$145.34 / EAIncludes 10% overhead and 10% fee
- Concrete washout container, prefabricated 6 ft x 6 ft$233.59 / EAIncludes 10% overhead and 10% fee
- Dewatering pump, 4 in, per pump-day$403.62 / EAIncludes 10% overhead and 10% fee
- Dewatering sump pit$661.17 / EAIncludes 10% overhead and 10% fee
- Dozer cut to fill, 100 ft push$1.55 / CYIncludes 10% overhead and 10% fee
- Dozer cut to fill, 200 ft push$2.12 / CYIncludes 10% overhead and 10% fee
- Dozer cut to fill, 300 ft push$2.90 / CYIncludes 10% overhead and 10% fee
- Erosion control blanket$0.29 / SFIncludes 10% overhead and 10% fee
- Export clean soil off-site, 10 miles$16.75 / CYIncludes 10% overhead and 10% fee
- Fiber roll (wattle), 9 in$3.60 / LFIncludes 10% overhead and 10% fee
- Fine grading, motor grader$0.12 / SFIncludes 10% overhead and 10% fee
- Footing excavation, continuous 24 x 30 in$6.33 / LFIncludes 10% overhead and 10% fee
- Footing excavation, spread footing$153.54 / EAIncludes 10% overhead and 10% fee
- Foundation wall backfill, free-draining$51.78 / CYIncludes 10% overhead and 10% fee
- Foundation wall backfill, native$11.54 / CYIncludes 10% overhead and 10% fee
- Geotextile, nonwoven separation$0.23 / SFIncludes 10% overhead and 10% fee
- Geotextile, woven stabilization$0.20 / SFIncludes 10% overhead and 10% fee
- Hand excavation, spot$74.31 / CYIncludes 10% overhead and 10% fee
- Haul excavated material off site, 15 mi$13.20 / CYIncludes 10% overhead and 10% fee
- Haul excavated material off site, 25 mi$18.16 / CYIncludes 10% overhead and 10% fee
- Haul excavated material off site, 30 mi$19.94 / CYIncludes 10% overhead and 10% fee
- Import common fill$29.27 / CYIncludes 10% overhead and 10% fee
- Import structural fill$43.27 / CYIncludes 10% overhead and 10% fee
- Inlet protection, curb inlet$69.40 / EAIncludes 10% overhead and 10% fee
- Inlet protection, grate inlet$84.11 / EAIncludes 10% overhead and 10% fee
- Mass excavation, common earth$2.27 / CYIncludes 10% overhead and 10% fee
- Off-site haul, 5 miles$6.91 / CYIncludes 10% overhead and 10% fee
- Off-site haul, 10 miles$10.00 / CYIncludes 10% overhead and 10% fee
- Off-site haul, 20 miles$15.71 / CYIncludes 10% overhead and 10% fee
- On-site haul, up to 2,000 ft$3.19 / CYIncludes 10% overhead and 10% fee
- Over-excavation and recompaction$6.14 / CYIncludes 10% overhead and 10% fee
- Pipe bedding and haunch, stone$68.94 / CYIncludes 10% overhead and 10% fee
- Rock check dam$225.58 / EAIncludes 10% overhead and 10% fee
- Rock excavation, hydraulic hammer$36.88 / CYIncludes 10% overhead and 10% fee
- Rock excavation, rippable$9.12 / CYIncludes 10% overhead and 10% fee