Metal stud partition 12ga

$18.79 / LF

DW-075 · MasterFormat 09 22 00 · LF

What’s in this rate

This unit is framing one linear foot of 12-gauge metal-stud partition, with track and studs amortized along the wall run. The carpenter cuts and fastens the framing ready for hang.

Includes

  • 12-gauge studs and track with 5% waste plus fasteners
  • cut, set track, and install studs
  • small tools

Excludes

  • drywall hang
  • deflection track
  • kickers
  • backing
  • door frames
  • engineering

Build-up

Labor 0.175 hr × $55.00 wage and burden
$9.62
Material and small tools
$5.91
Direct rate (labor, material, and tools)
$15.53 / LF
Overhead 10% of direct
$1.55
Fee 10% of (direct and overhead)
$1.71
Loaded rate
$18.79 / LF