Control joint in CMU
$11.03 / LF
MS-012 · MasterFormat 04 22 00 · LF
What’s in this rate
This unit covers Control joint in CMU, measured per linear foot. The bricklayer forms a vertical control joint in the CMU wall and installs the scoped gasket or filler. The rate covers the listed material, 5.00% material waste, labor, and small tools. masonry control joint gasket, brick expansion joint, drywall/concrete control joints are separate units.
Includes
- vertical control joint cut/slot in CMU
- premolded gasket or filler allocation as scoped
- layout and installation described above
- stated material waste and small tools
Excludes
- drywall control joint
- concrete control joint
- brick expansion joint
- tax / freight
- after-hours, premium access, and hazardous-material handling
Build-up
- Labor 0.12 hr × $52.00 wage and burden
- $6.24
- Material and small tools
- $2.88
- Direct rate (labor, material, and tools)
- $9.12 / LF
- Overhead 10% of direct
- $0.91
- Fee 10% of (direct and overhead)
- $1.00
- Loaded rate
- $11.03 / LF