Pile cap pour

$26.96 / CF

CN-169 · MasterFormat 03 30 00 · CF

What’s in this rate

This unit is placing one cubic foot of concrete into a prepared pile-cap form. The cement mason places, consolidates, and finishes the pile-cap mass. Excavation, formwork, reinforcing steel, piles, and testing are separate units.

Includes

  • ready-mix concrete
  • tremie and curing-material allowance
  • place, consolidate, and finish pile cap
  • small tools

Excludes

  • excavation
  • formwork
  • reinforcing steel
  • piles and anchors
  • pump mobilization
  • testing

Build-up

Labor 0.285 hr × $48.00 wage and burden
$13.68
Material and small tools
$8.60
Direct rate (labor, material, and tools)
$22.28 / CF
Overhead 10% of direct
$2.23
Fee 10% of (direct and overhead)
$2.45
Loaded rate
$26.96 / CF

Use this in a private library

Create a free account to keep your own hours, burden, and supplier quotes behind a login. Published rates stay public. Your own hours and quotes stay private.