Building pad excavation, common earth — $3.04/CY

New Construction

$3.04 / CY

Building pad excavation, common earth — $3.04/CY costs about $3.04 per cubic yard installed. This is a published starting point and varies by region and job.

EW-S1-001 · MasterFormat 31 23 16 · CY

What’s in this rate

This unit is bank cubic yards of common earth cut for a commercial building pad to design subgrade, loaded onto trucks. Haul-off, rock, over-excavation, fill, and fine grade are separate units. Production assumes open-site machine work with pad perimeter grade control.

Includes

  • cut building pad to design subgrade (bank CY)
  • load haul trucks
  • pad perimeter grade check / spotter
  • operator and laborer time and equipment listed in the build-up
  • stated material waste and small tools

Excludes

  • haul and disposal (earthwork-haul-* / export)
  • rock excavation
  • over-excavation and recompaction
  • structural fill / aggregate base
  • fine grading
  • shoring
  • dewatering
  • tax / freight beyond stated prices
  • after-hours, premium access, contaminated soil
  • geotechnical testing, surveying / staking, permits

Build-up

Operator, 0.012 hr × $53.00
$0.64
Laborer, 0.006 hr × $41.00
$0.24
Material and small tools
$0.01
Equipment, hydraulic excavator ~35 t / ~1.5–2 CY bucket class, 0.012 hr per unit
$1.62
Direct rate (labor, material, equipment, and tools)
$2.51 / CY
Overhead 10% of direct
$0.25
Fee 10% of (direct and overhead)
$0.28
Loaded rate
$3.04 / CY

Worked extension: 100 CY of commercial building pad excavation, common earth × $3.04 = $304.00 loaded for 100 CY. Quantity is a worked extension.