Fine grading, motor grader (large area)
$0.12 / SF
Fine grading, motor grader (large area) costs about $0.12 per square foot installed. This is a published starting point and varies by region and job.
EW-040 · MasterFormat 31 22 16 · SF
What’s in this rate
This is a production rate for motor-grader fine grading on large, open areas — building pads, parking lots and roadway subgrade — after rough grading is done. It covers a ~14 ft blade grader trimming to finish grade, a laborer checking grade, and a finish pass with a smooth-drum roller. It is priced per square foot and assumes large quantity with long grader passes; it is not a turnkey small-yard grading price. Hand fine grading in tight areas, mobilization, base stone and fill are priced with the related rates below.
Includes
- motor grader fine grade on large, open areas (production machine pass)
- grade checking
- finish roll
- operator and laborer time and equipment listed in the build-up
- stated material waste and small tools
Excludes
- small, tight or obstructed areas and equipment mobilization
- rough grading (earthwork-rough-grading)
- aggregate base (earthwork-aggregate-base-*)
- hand fine grading in tight areas
- tax / freight beyond the stated delivered material prices
- after-hours, premium access, and contaminated / hazardous soil handling
- geotechnical testing, surveying / staking, and permits
Build-up
- Operator, 0.00048 hr × $53.00
- $0.03
- Laborer, 0.00033 hr × $41.00
- $0.01
- Material and small tools
- $0.00
- Equipment, motor grader ~14 ft blade class, 0.00033 hr per unit
- $0.05
- Equipment, smooth-drum vibratory roller ~84 in class, 0.00015 hr per unit
- $0.01
- Direct rate (labor, material, equipment, and tools)
- $0.10 / SF
- Overhead 10% of direct
- $0.01
- Fee 10% of (direct and overhead)
- $0.01
- Loaded rate
- $0.12 / SF
Worked extension: 50,000 SF parking lot subgrade. At the build-up's production, that is roughly 16–17 grader hours, 7–8 roller hours, 24 operator hours and 16–17 laborer hours. Small areas will not reach this production; price them by the hour or as a minimum charge. × $0.12 = $6,000.00 loaded for 50,000 SF. Quantity is a worked extension.
Related rates
- Rough grading, dozer (large area) — $0.05 / SF
- Subgrade preparation and proof roll — $0.12 / SF
- Common fill, place and compact, 12 in lifts — $2.08 / CY
- On-site haul, up to 2,000 ft — $3.22 / CY
- Aggregate base, 4 in — $0.74 / SF
- Dozer cut to fill, 100 ft push — $1.56 / CY
- Dozer cut to fill, 200 ft push — $2.13 / CY
- Common fill, place and compact, 18 in lifts — $1.73 / CY
Use this in a private library