Tear-off, single-ply membrane

$163.35 / SQ

Tear-off, single-ply membrane costs about $163.35 per square (100 SF) installed. This is a published starting point and varies by region and job.

Tear-off, single-ply membrane · MasterFormat 07 01 50 · SQ

Dumpster and trailer prices

These haul prices are separate from the unit rate. Omaha, Nebraska is the 1.00 baseline. Another state uses that state's cost factor. Loaded is the direct price times 1.21, rounded half-up once.

Omaha, Nebraska

  • 10-yard dumpster direct $232.50, loaded $281.33.
  • 20-yard dumpster direct $325.00, loaded $393.25.
  • 30-yard dumpster direct $405.00, loaded $490.05.
  • Trailer trip direct $204.30, loaded $247.20. Tip $51.65 per ton direct, $62.50 per ton loaded.
  • Overage direct $70.00 per ton, loaded $84.70 per ton.

Texas

  • 10-yard dumpster direct $220.88, loaded $267.26.
  • 20-yard dumpster direct $308.75, loaded $373.59.
  • 30-yard dumpster direct $384.75, loaded $465.55.
  • Trailer trip direct $194.09, loaded $234.84. Tip $49.07 per ton direct, $59.37 per ton loaded.
  • Overage direct $66.50 per ton, loaded $80.47 per ton.

California

  • 10-yard dumpster direct $279.00, loaded $337.59.
  • 20-yard dumpster direct $390.00, loaded $471.90.
  • 30-yard dumpster direct $486.00, loaded $588.06.
  • Trailer trip direct $245.16, loaded $296.64. Tip $61.98 per ton direct, $75.00 per ton loaded.
  • Overage direct $84.00 per ton, loaded $101.64 per ton.

Open the dumpster price calculator for another state.

What’s in this rate

This unit is removing an existing single-ply membrane. The crew cuts and pulls the sheet, backs out plates and fasteners, and loads debris. The rate is per square (100 square feet). New TPO, insulation, and cover board are separate units.

Includes

  • Cut and strip the existing single-ply field sheet
  • Pull plates and fasteners from the membrane layer
  • Load dumpster
  • Sweep the work area
  • Small tools

Excludes

  • Insulation tear-off
  • Wet or multi-layer built-up and mod-bit
  • Asbestos testing or abatement
  • Deck repair
  • New membrane

Build-up

Labor 2 hr × $65.00 wage and burden
$130.00
Material and small tools
$5.00
Direct rate (labor, material, and tools)
$135.00 / SQ
Overhead 10% of direct
$13.50
Fee 10% of (direct and overhead)
$14.85
Loaded rate
$163.35 / SQ