Stabilized construction entrance
$3,215.07 / EA
EW-010 · MasterFormat 31 25 13 · EA
What’s in this rate
This unit covers Stabilized construction entrance, measured per each. The crew lays geotextile and places and spreads a 12-inch crushed-stone pad at the site exit. The rate covers the listed material, labor, and small tools. Top-dressing, wheel wash, street sweeping, and SWPPP maintenance stay on their own units.
Includes
- nonwoven geotextile ~1,000 SF
- 2–3 in crushed stone 12 in thick (~20x50 ft)
- loader placement and spreading
- operator and laborer time and equipment listed in the build-up
- stated material waste and small tools
Excludes
- SWPPP plan preparation, inspections, reporting, and permit fees
- maintenance, sediment cleanout, and removal at project end
- wheel-wash rack / rumble plates
- street sweeping
- stone top-dressing over the job
- tax / freight beyond the stated delivered material prices
- after-hours, premium access, and contaminated / hazardous soil handling
- geotechnical testing, surveying / staking, and permits
Build-up
- Operator, 3 hr × $52.00
- $156.00
- Laborer, 4 hr × $38.00
- $152.00
- Material and small tools
- $2,019.08
- Equipment, wheel loader ~3 CY class, 3 hr per unit
- $330.00
- Direct rate (labor, material, equipment, and tools)
- $2,657.08 / EA
- Overhead 10% of direct
- $265.71
- Fee 10% of (direct and overhead)
- $292.28
- Loaded rate
- $3,215.07 / EA
Worked extension: 1 EA of commercial stabilized construction entrance × $3,215.07 = $3,215.07 loaded for 1 EA. Quantity is a worked extension.