Structural fill, 12 in lifts
$2.84 / CY
Structural fill, 12 in lifts costs about $2.84 per cubic yard installed. This is a published starting point and varies by region and job.
EW-035 · MasterFormat 31 23 23 · CY
What’s in this rate
This unit covers Structural fill, 12 in lifts, measured per cubic yard. The operator spreads fill in 12-inch lifts, moisture-conditions it, and compacts it with a vibratory roller. The rate covers the listed material, labor, and small tools. Fill material, testing, and thinner-lift placement stay on their own units.
Includes
- spread in 12 in loose lifts
- moisture condition
- sourced water at the utility volumetric rate
- vibratory roller compaction
- operator and laborer time and equipment listed in the build-up
- stated material waste and small tools
Excludes
- fill material (earthwork-import-*)
- compaction testing
- fine grading
- tax / freight beyond the stated delivered material prices
- after-hours, premium access, and contaminated / hazardous soil handling
- geotechnical testing, surveying / staking, and permits
- hydrant meter set and monthly fees
Build-up
- Operator, 0.014 hr × $53.00
- $0.74
- Laborer, 0.004 hr × $41.00
- $0.17
- Water
- Portland Water District volumetric rate, $0.11 per CY
- Material and small tools
- $0.12
- Equipment, crawler dozer ~D6 class, 0.005 hr per unit
- $0.65
- Equipment, smooth-drum vibratory roller ~84 in class, 0.0065 hr per unit
- $0.55
- Equipment, water truck ~2,000–4,000 gal (driven by Operator), 0.0025 hr per unit
- $0.12
- Direct rate (labor, material, equipment, and tools)
- $2.35 / CY
- Overhead 10% of direct
- $0.24
- Fee 10% of (direct and overhead)
- $0.25
- Loaded rate
- $2.84 / CY
Worked extension: 100 CY of commercial structural fill, 12 in lifts × $2.84 = $284.00 loaded for 100 CY. Quantity is a worked extension.
Related rates
- Export clean soil off-site, 10 miles — $16.77 / CY
- Structural fill, 8 in lifts — $3.75 / CY
- Structural fill, place and compact, 10 in lifts — $3.25 / CY
- Common fill, place and compact, 12 in lifts — $2.08 / CY
- Common fill, place and compact, 18 in lifts — $1.73 / CY
- Structural fill, 6 in lifts — $4.78 / CY
- Subgrade preparation and proof roll — $0.12 / SF
- Rough grading, dozer (large area) — $0.05 / SF