Structural fill, place and compact, 10 in lifts
$3.25 / CY
Structural fill, place and compact, 10 in lifts costs about $3.25 per cubic yard installed. This is a published starting point and varies by region and job.
EW-062 · MasterFormat 31 23 23 · CY
What’s in this rate
This unit covers structural fill, place and compact, 10 in lifts, measured per cubic yard. The operator spreads fill in 10-inch lifts, moisture-conditions it, and compacts it with a vibratory roller. The rate covers the listed material, sourced water, labor, and small tools. Fill material, compaction testing, and fine grading stay on their own units.
Includes
- spread in 10 in loose lifts
- sourced water at the utility volumetric rate
- moisture condition (water-truck time)
- vibratory roller compaction
- operator and laborer time and equipment listed in the build-up
- stated material waste and small tools
Excludes
- fill material (earthwork-import-*)
- sourced water at the utility volumetric rate
- hydrant meter set and monthly fees
- compaction testing
- fine grading
- sales tax; freight beyond what the build-up states
- after-hours, premium access, and contaminated / hazardous soil handling
- geotechnical testing, surveying / staking, and permits
Build-up
- Operator, 0.01625 hr × $53.00
- $0.86
- Laborer, 0.0045 hr × $41.00
- $0.19
- Water
- Portland Water District volumetric rate, $0.11 per CY
- Material and small tools
- $0.12
- Equipment, crawler dozer ~D6 class, 0.0055 hr per unit
- $0.71
- Equipment, smooth-drum vibratory roller ~84 in class, 0.008 hr per unit
- $0.68
- Equipment, water truck ~2,000–4,000 gal (driven by Operator), 0.00275 hr per unit
- $0.13
- Direct rate (labor, material, equipment, and tools)
- $2.69 / CY
- Overhead 10% of direct
- $0.27
- Fee 10% of (direct and overhead)
- $0.29
- Loaded rate
- $3.25 / CY
Worked extension: 100 CY of commercial structural fill, place and compact, 10 in lifts × $3.25 = $325.00 loaded for 100 CY. Quantity is a worked extension.
Related rates
- Structural fill, 12 in lifts — $2.84 / CY
- Structural fill, 8 in lifts — $3.75 / CY
- Structural fill, 6 in lifts — $4.78 / CY
- Common fill, place and compact, 12 in lifts — $2.08 / CY
- Common fill, place and compact, 18 in lifts — $1.73 / CY
- Subgrade preparation and proof roll — $0.12 / SF
- Rough grading, dozer (large area) — $0.05 / SF
- Fine grading, motor grader (large area) — $0.12 / SF