Earthwork unit rates
Page 2 of 2
Published earthwork unit rates, Division 31: clearing, erosion control, excavation, haul, fill, grading, and trench backfill. Each page is one unit with a loaded price.
Also see electrical unit rates, low-voltage unit rates, roofing unit rates, drywall unit rates, painting unit rates, concrete unit rates, flooring unit rates, plumbing unit rates, HVAC unit rates, fire protection unit rates, masonry unit rates, structural steel unit rates, siding unit rates, tile unit rates, windows and doors unit rates, and cabinets and countertops unit rates.
- Mass excavation, common earth$3.00 / CYIncludes 10% overhead and 10% fee
- Mulch Bed 3"New Construction$0.85 / SFIncludes 10% overhead and 10% fee
- Off-site haul, 5 miles$6.92 / CYIncludes 10% overhead and 10% fee
- Off-site haul, 10 miles$10.01 / CYIncludes 10% overhead and 10% fee
- Off-site haul, 20 miles$15.72 / CYIncludes 10% overhead and 10% fee
- On-site haul, up to 2,000 ft$3.22 / CYIncludes 10% overhead and 10% fee
- Over-excavation and recompaction$6.09 / CYIncludes 10% overhead and 10% fee
- Pipe bedding and haunch, stone$69.90 / CYIncludes 10% overhead and 10% fee
- Pressure-treated wood deck installedNew Construction$19.30 / SFIncludes 10% overhead and 10% fee
- Rock check damNew Construction$229.82 / EAIncludes 10% overhead and 10% fee
- Rock excavation, hydraulic hammer$34.56 / CYIncludes 10% overhead and 10% fee
- Rock excavation, rippable$9.17 / CYIncludes 10% overhead and 10% fee
- Rough grading, dozer (large area)$0.05 / SFIncludes 10% overhead and 10% fee
- Shrub Planting, 3-GallonNew Construction$69.19 / EAIncludes 10% overhead and 10% fee
- Silt fence$2.06 / LFIncludes 10% overhead and 10% fee
- Silt fence, wire-backed$3.99 / LFIncludes 10% overhead and 10% fee
- Stabilized construction entranceNew Construction$3,233.22 / EAIncludes 10% overhead and 10% fee
- Structural fill, 6 in lifts$4.78 / CYIncludes 10% overhead and 10% fee
- Structural fill, 8 in lifts$3.75 / CYIncludes 10% overhead and 10% fee
- Structural fill, 12 in lifts$2.84 / CYIncludes 10% overhead and 10% fee
- Structural fill, place and compact, 10 in lifts$3.25 / CYIncludes 10% overhead and 10% fee
- Subgrade preparation and proof roll$0.12 / SFIncludes 10% overhead and 10% fee
- Topsoil respread from stockpile, 4 in$0.04 / SFIncludes 10% overhead and 10% fee
- Topsoil respread from stockpile, 6 in$0.06 / SFIncludes 10% overhead and 10% fee
- Topsoil stripping, 6 in$0.04 / SFIncludes 10% overhead and 10% fee
- Topsoil stripping, 12 in$0.07 / SFIncludes 10% overhead and 10% fee
- Trench backfill, native$8.95 / CYIncludes 10% overhead and 10% fee
- Trench backfill, select granular$47.44 / CYIncludes 10% overhead and 10% fee
- Trench excavation, 18 in wide x 3 ft deep$3.30 / LFIncludes 10% overhead and 10% fee
- Trench excavation, 18 in wide x 4 ft deep$4.03 / LFIncludes 10% overhead and 10% fee
- Trench excavation, 24 in wide x 4 ft deep$5.11 / LFIncludes 10% overhead and 10% fee
- Trench excavation, 24 in wide x 5 ft deep$6.98 / LFIncludes 10% overhead and 10% fee
- Trench excavation, 24 in wide x 6 ft deep$8.37 / LFIncludes 10% overhead and 10% fee
- Trench excavation, 30 in wide x 6 ft deep$9.68 / LFIncludes 10% overhead and 10% fee
- Trench excavation, 30 in wide x 8 ft deep$13.08 / LFIncludes 10% overhead and 10% fee
- Trench excavation, 36 in wide x 8 ft deep$17.98 / LFIncludes 10% overhead and 10% fee
- Trench excavation, 36 in wide x 10 ft deep$23.49 / LFIncludes 10% overhead and 10% fee
- Trench excavation, 48 in wide x 8 ft deep$28.71 / LFIncludes 10% overhead and 10% fee
- Trench excavation, 48 in wide x 10 ft deep$34.46 / LFIncludes 10% overhead and 10% fee
- Wood fence removalRemoval$9.52 / LFIncludes 10% overhead and 10% fee
- Wood privacy fence 6 ftNew Construction$36.81 / LFIncludes 10% overhead and 10% fee